  Proper Invoice, Ontario

Ontario Construction Act Proper Invoice: The 28-Day Clock and Your Checklist.

What the Construction Act says about a proper invoice, the 28-day owner payment deadline, notices of non-payment and adjudication limits, read from e-Laws, with a checklist and an invoice-check automation where a person approves every date.

28 daysOwner payment deadline after a proper invoice, Construction Act s 6.4(1)
14 daysOwner notice of non-payment window, s 6.4(2)
A person approvesThe system checks and proposes dates; a person confirms each one

In Ontario, the date that starts the payment clock is not the date you finish the work or the date you send the bill. It is the date the owner receives a proper invoice. If the invoice is missing something the Construction Act requires, a dispute about whether the clock started at all can cost weeks. That is one small document with one very expensive job.

Devvista is a software development company that designs workflow automation for contractors, including invoice checking and deadline tracking around prompt payment. This page sets out what the Ontario Construction Act says about proper invoices, the 28-day owner payment deadline, notices of non-payment and adjudication, based on the e-Laws text we read, and then describes an automation that checks an invoice against the statutory contents, starts the deadline clocks and leaves every date for a person to approve. It is general information, not legal advice. To discuss it, describe how invoices move through your business.

01

Which Version of the Act We Read

Ontario has amended its Construction Act several times in recent years, and some online summaries disagree on dates. We therefore say exactly which text we read. We opened the Act on ontario.ca e-Laws on 11 November 2026. It was marked CURRENT, with a consolidation period of January 1, 2026 to the e-Laws currency date of November 5, 2026, and a last amendment of 2025, c. 14, Sched. 2 (Construction Act, R.S.O. 1990, c. C.30).

e-Laws marks provisions that are not yet in force with an editorial note. In the version we read, the only such notes concern the definition of "home buyer" in section 1(1) and a provision in section 39(1). Neither is part of what follows. We did not read the table of in-force dates for each amendment, so we do not state when individual changes started. If a date matters to your contract, check that table on e-Laws or ask a construction lawyer.

02

What Is a Proper Invoice in Ontario? A Seven-Item Checklist

Section 6.1(1) defines a proper invoice as a written bill or other request for payment for services or materials in respect of an improvement under a contract. It must contain the items below and, subject to section 6.3(2), meet any other requirements the contract specifies. We have turned the statutory list into a checklist you can use today.

#What the Act says the invoice must contain (s 6.1(1))Check on your invoice
1The contractor's name and addressIs the legal name and address on the invoice?
2The date of the invoice and the period, milestone or other contractual payment entitlement to which it relatesIs the date there, and is the billing period or milestone named?
3Information identifying the contract or other authorization under which the services or materials were supplied, such as a contract number, line item number or purchase order numberIs the contract or purchase order number on the invoice?
4A description, including quantity where appropriate, of the services or materials suppliedIs each item described, with quantities where they apply?
5The amount payable for the services or materials supplied, and the payment termsIs the amount clear, and are the terms stated?
6The name, title, mailing address and telephone number of the person to whom payment is to be sent, or the name, mailing address and telephone number of the office or departmentIs there a payee contact with those four details?
6.1Any other information necessary for the proper functioning of the owner's accounts payable system that the owner reasonably requestsHas the owner asked for anything else, such as a vendor number or approval code?
7Any other information that may be prescribedCheck the regulations for anything prescribed; we did not read them

Two related rules change how strict this is in practice. Under section 6.1(2), an invoice that falls short still counts as proper unless the owner tells the contractor in writing, within seven days of receiving it, what is missing and what would fix it. Section 6.3(2) says a contract term that makes the giving of a proper invoice conditional on prior certification by a payment certifier or on the owner's prior approval has no force or effect.

03

The Prompt Payment Clocks: 7, 14, 28 and 35 Days

Once a proper invoice is received, the Act sets the clocks. We quote the sections we read. The Act says "days", and we did not read how days are counted, for instance across weekends, so confirm the counting method before relying on a computed date.

ClockWhat the Act saysSection
Invoice frequencyProper invoices are to be given to an owner monthly, unless the contract provides otherwise6.3(1)
Owner deficiency noticeAn invoice that falls short is deemed proper unless the owner notifies the contractor in writing within seven days of receiving it, stating the deficiency and what is required6.1(2)
Owner payment deadlineThe owner shall pay the amount payable under a proper invoice no later than 28 days after receiving it, subject to a notice of non-payment6.4(1)
Owner notice of non-paymentTo refuse all or part of the amount, the owner must give a notice of non-payment, in the prescribed form and manner, no later than 14 days after receiving the proper invoice, specifying the amount not paid and detailing all the reasons6.4(2)
Contractor pays subcontractorsAfter receiving full payment, the contractor shall pay each subcontractor whose work was in the invoice no later than seven days after receiving payment6.5(1)
Contractor, partial paymentSame seven days, from the amount paid, with rules for sharing it rateably between subcontractors6.5(2), (3)
Contractor, owner has not paidSubject to a notice, the contractor shall pay the subcontractor no later than 35 days after giving the proper invoice to the owner6.5(4)
Contractor notice to subcontractorTo rely on the owner's non-payment, the contractor must give a notice of non-payment, with an undertaking to refer the matter to adjudication within 21 days, no later than seven days after receiving the owner's notice, or if there was none, before the 35 days expire6.5(5), (7)
Payment is subject to holdbackAny requirement to pay under this Part is subject to the holdback requirements in Part IV6.2

The text says the same pattern continues down the chain: section 6.6 applies timing rules to payments between subcontractors. We did not read it in detail for this page.

04

Adjudication Time Limits We Could Confirm

If a dispute about a proper invoice or a notice of non-payment cannot be settled, the Act has an adjudication process in Part II.1. We read two provisions that matter for deadline tracking and we leave out the rest of the procedure, which includes prescribed forms we did not read.

PointWhat the Act saysSection
Time limit to start an adjudication under a contractAn adjudication may not be commenced if the notice of adjudication is given more than 90 days after the contract is completed, abandoned or terminated, unless the parties agree otherwise13.5(3)
Time limit under a subcontractMore than 90 days after the earliest of: the contract date above, the date the subcontract is certified complete under section 33, and the date the subcontractor last supplied services or materials13.5(3.1)
Adjudicator's determinationNo later than 30 days after receiving the documents required by section 13.11; this can be extended by up to 14 days with the parties' written consent, or by longer written agreement13.13(1), (2)
What can be adjudicatedDisputes on matters prescribed by regulation, or any matter the parties agree to13.5(1), (2)

The regulations prescribe the matters. A search result pointed to Ontario Regulation 264/25 on adjudications, but we did not open it, so we do not list the prescribed matters here.

05

Annual Holdback Release in the Current Text

You may also have heard that holdback release changed. The text we read includes section 26, headed "Payment of basic holdback". It says that following each anniversary of the date the contract was entered into, the owner shall publish a notice of annual release of holdback no later than 14 days after the anniversary, then pay the accrued holdback for the preceding year at least 60 days but not later than 74 days after that notice is published, unless a lien has been preserved or perfected. The contractor must then pay a subcontractor its accrued holdback no later than 14 days after receiving payment (s 26(2) to (5)).

We did not read the transition rules that decide which contracts this applies to, and e-Laws attaches its in-force dates to a separate table. So we give you the clocks as written and we recommend your adviser confirms whether and how they apply to a given contract. For a tracker, the practical point is that holdback creates a second set of dates beside the invoice dates, tied to the contract anniversary.

06

Where Manual Invoicing Loses Money

Most of the cost of a proper-invoice dispute is lost time, not law. These are the places it goes missing.

Where it leaksWhat goes wrongWhy it costs money
Invoices are built from a template by handThe contract or purchase order number, the billing period or the payee contact is left offThe owner can argue the invoice was not proper, and the 28 days is contested
The owner's accounts payable team asks for an extra fieldThe request is not seen or not metSection 6.1(1) item 6.1 lets the owner reasonably ask for it
Nobody records when the owner received the invoiceThe 28, 14 and 7 day dates are counted from the day it was sentYou chase on the wrong date, or the owner serves a notice you assume is late
A notice of non-payment arrives by email and is read days laterThe seven day window for a contractor's notice to a subcontractor is already runningA missed notice can leave you carrying the owner's non-payment
Subcontractor payments tracked in a separate spreadsheetThe seven day and 35 day clocks are not linked to the owner invoiceYou pay late, or pay before you know whether you were paid
Holdback anniversaries live in someone's headThe notice date and the 60 to 74 day payment window go unnoticedCash that was due is released late

Notice how many are record-keeping problems. A system that stores the received date, the invoice contents and every notice in one place removes most of them.

07

A Proper-Invoice Tracker You Can Copy

You can start with a sheet. Use one row per invoice and add these columns.

ColumnWhat goes in it
Invoice number, contract and purchase order numbersTo match the statutory identification item
Billing period or milestoneTo match the statutory period item
Checklist result for items 1 to 7Pass, or the missing item
Date sent, date received (with proof)The date received starts the clocks
Owner deficiency window endsDate received plus seven days
Owner notice of non-payment window endsDate received plus 14 days
Owner payment dueDate received plus 28 days
Subcontractor payment dueSeven days after you are paid; and the 35-day outer date from the day you gave the invoice
Adjudication outer date90 days from the relevant completion, abandonment or termination date
Confirmed by (name, date)The person who checked the dates

Every date in the sheet is a candidate. The person who confirms it checks the contract and the Act, including how days are counted.

08

The Automation: Check Before You Send, Start the Clocks, a Person Approves

The automation has two jobs: stop a bad invoice leaving the building, and start the right clocks the moment one is received. We would build it in five stages.

StageWhat the system doesWho decides
1. ReceiveCollects invoices from the sources you choose: email, a portal download or a folder. Stores the original and the date and time it was received or sentNobody: it is filing
2. ReadClaude reads the invoice, extracts the fields in the statutory list and the amount, and shows each extracted value next to the originalA person checks anything marked uncertain
3. CheckCompares the extracted fields with the seven items in s 6.1(1) and with the extra requirements in the contract that you have recorded. Lists what is missing, in plain words, before the invoice is sentA person decides whether to send, fix or ask the owner
4. Start the clocksOn confirmed receipt, proposes the seven, 14 and 28 day dates, the 35-day and seven-day subcontractor dates and, where relevant, the 90-day adjudication dateA person confirms each date
5. Alert and recordReminds the right people before each date, records any notice received or sent with its time, and keeps one timeline for the invoiceA person acts on every alert

A second use is on the owner side. An owner or main contractor that receives invoices can have the system check them against the same list and flag, within the seven-day window in s 6.1(2), any deficiency a person may want to notify in writing. The decision to notify stays with a person.

For the build we would usually start with n8n or Make, which connect email, folders, spreadsheets and accounting systems quickly, and add custom code where a rule is particular to your contracts. This is a design description. We are not citing a client result for it, and we do not claim a construction case study.

09

Contracts, Invoices and Confidentiality

Contracts and invoices carry commercial terms and sometimes personal information. Before any AI model reads them, we would ask you to check the confidentiality terms of your contracts, decide which documents may be sent to a model, and record which model and where it runs. We would restrict who can see the documents, log who confirmed each date and agree how long records are kept. We are developers, not lawyers, and we do not make a statement here about privacy law. Ask your adviser about your obligations.

10

When Not to Automate

Not every Ontario contractor needs this. We would suggest something simpler if any of these is true.

Your situationWhat we would suggest
You send a few invoices a month on one or two contractsThe checklist above and a calendar. The system costs more than the problem
Your accounting package already produces invoices with all the required fields and you track dates thereUse it. Add only a received-date log
There is a live payment dispute or an adjudication notice has been givenSpeak to a construction lawyer now. Software cannot repair a missed date
You want the system to decide whether an invoice is properWe would not build that. We check against a list and a person decides
You also work in other provincesThe rules differ. We have not covered other provinces here, so we would research each first

If a simpler option fits, we will say so on the first call. For the wider picture of what can be automated in a contractor's office, see our AI automation page and the US hub on AI automation for construction companies. The method carries across countries, but the rules do not.

11

How a Build Runs and What Moves the Quote

A first release is usually one contract type and one inbox. Here is how we would propose to run it.

  1. Walk through three real invoices. We look at what was sent, what was received and what the dates actually were.
  2. Write the checklist and rules with you. Statutory items, the contract extras and who confirms what, reviewed by your adviser.
  3. Test on past invoices. The system flags what was missing and proposes dates, and you compare them with history.
  4. Run beside your current routine. Alerts fire, a person confirms, nothing is relied on until it matches.
  5. Extend. Add subcontractor payments, holdback anniversaries or the owner side.

Prices vary with scope. What moves a quote is the number of contracts and invoice formats, how invoices reach you, whether you track subcontractor payments and holdback as well, and which accounting or project systems the alerts must reach. Calls, demos and releases are held on video. We begin with a short call about your budget range, then propose a scope that fits it. Our construction software and custom software development pages cover the wider systems.

12

Who This Suits and Your Next Step

This suits Ontario contractors and subcontractors who send several invoices a month, owners and main contractors who receive many, and anyone who has argued about whether a proper invoice was given. It does not suit a business that wants a verdict on its legal rights.

A good fitProbably not
Several contracts and invoices a monthA few invoices a year
Invoices arrive in different formatsA single template, always complete
A person will confirm every dateYou want dates trusted blindly
You want one timeline per invoice, including noticesYou want a legal opinion

To start, use the contact form, tell us roughly how many invoices you send or receive in a month and the budget range you have in mind. We will come back after a short call with a written proposal. For a site-team tool that captures documents from the field, see our mobile app development page. Back to the Canada home page.

Straight Answers.

Still have a question?Send it over and we will answer personally.Send Your Question

Section 6.1(1) defines it as a written bill or request for payment that contains the contractor's name and address, the invoice date and the period or milestone it covers, information identifying the contract, a description of the services or materials, the amount payable and payment terms, payee contact details, any other information the owner reasonably requests for its accounts payable system, and anything prescribed.

Section 6.4(1) says no later than 28 days after receiving the proper invoice, subject to a notice of non-payment. The payment is also subject to any holdback required under Part IV.

Section 6.4(2) says no later than 14 days after receiving the proper invoice, in the prescribed form and manner, specifying the amount not paid and detailing all the reasons.

Under section 6.1(2) an invoice that falls short is deemed to be a proper invoice unless the owner notifies the contractor in writing, no later than seven days after receiving it, of the deficiency and what is needed. So the owner has a short window to object.

Section 6.5(1) says no later than seven days after the contractor receives full payment. If the owner has not paid, section 6.5(4) says no later than 35 days after giving the proper invoice to the owner, unless a notice of non-payment is given. These are general timing rules, and your contract and the notices given decide the details.

Section 13.5(3) says an adjudication under a contract cannot be commenced if the notice is given more than 90 days after the contract is completed, abandoned or terminated, unless the parties agree otherwise. Section 13.5(3.1) sets a related rule for subcontracts.

The e-Laws text we read on 11 November 2026 was marked current from January 1, 2026, with a last amendment of 2025, c. 14, Sched. 2. It includes the seven-day deficiency rule and an annual holdback release process. We did not read the table that lists each amendment's in-force date, so we do not state commencement dates.

Yes. A system can extract the fields, compare them with the seven items and any contract extras, and list what is missing before the invoice goes out. A person decides whether to send it.

Yes. A model such as Claude can read an invoice or a contract, extract the fields and show each next to the original. Check your contracts' confidentiality terms first, and record which model is used and where it runs.

We have not opened the BC or Alberta statutes for this page, so we say nothing about them. The rules differ by province, and we would research each before building for it.

It depends on the number of contracts and invoice formats, how invoices reach you, whether you track subcontractor payments and holdback and which systems the alerts reach. On a short call you tell us the budget range you have in mind, and we come back with a proposal that fits it.

No. It is general information from the e-Laws text read on 11 November 2026. The Act can change, and your contract matters. For a payment dispute, speak to a construction lawyer.
Canada

Tell us how invoices move through your business

Describe your contracts, how invoices are sent or received and what systems you use. Book a call and we will say what to automate, what to leave to a person and what the first release should contain.

  • 30-minute online call
  • Honest feedback on fit
  • No obligation
  1. Book a call30 minutes online. Tell us what you want to build.
  2. Get a straight answerHonest feedback on fit and scope.
  3. DecideYou choose the next step once the scope is clear.
Chat on WhatsApp